Drillers onsite at 7:40 to layout bore hole
Drilling first Battered hole, most north one.
Finished first preview at 12:00, moving rig to other batter hole
Moved to next hole, hit part of old bridge
Finished second hole and moved to next hole. Had to layout holes do to rig taking them out.
Started third hole at 1:20, all holes hitting rock around 5 feet down.
Finished third hole 3:10, moved to last hole.
Contractor is planning on pouring Back walls on Friday on Bents 1 & 3.